Timeline
- Research and Planning: [29/July/2024] to [31/July/2024]
- Design and Development: [01/August/2024] to [05/October/2024]
- Figma Design : [01/August/2024] to [31/August/2024]
- Design IA Structure
7days
- Create WireFrame
3days
- Create UI Screen
10days
- Design Flow Planning
1day
- Design Flow Guide
2days
- SQL ERD
7days
- Development : [01/September/2024] to [05/October/2024]
- Project Setup, Database Design, Initial API Development
One Week
- Authentication & Authorization
One Week
- User Management, Attendance Management, User Functionalities
One Week
- Frontend Development
Two Weeks
- Testing and Debugging: [06/October/2024] to [13/October/2024]
- Optimization and Documentation: [14/October/2024] to [15/October/2024]
- Deployment: [16/October/2024] to [20/October/2024]
Resource and Tools
- Backend:
Node.js
, Express.js
, Sequelize
, MySQL
- Frontend:
React.js
, Axios
, React Router
, React Redux Toolkit Query
- Deployment:
AWS EC2
, AWS RDS
, AWS VPC
, ROUTE 53
, AMPLIFY
- Version Control:
Git
, GitHub